RFIs get a bad reputation on construction projects — too many, too slow, too often the cause of a delay. But the problem usually isn't RFIs themselves; it's a broken RFI process. A well-run RFI workflow surfaces problems early and resolves them fast. A poorly run one lets questions pile up unanswered until work stalls. This guide walks through the RFI process step by step and the best practices that keep it moving.

The RFI process, step by step

1. A question arises. Someone in the field or the office finds a conflict, gap, or ambiguity in the documents, or a field condition that doesn't match the plans.

2. The RFI is written. The question is documented clearly, with references, the field condition, a proposed solution, and the schedule impact.

3. The RFI is submitted and logged. It goes to the responsible party (often the architect or engineer) and is entered in the RFI log with a number, submission date, and required-by date.

4. The RFI is reviewed and answered. The recipient investigates and issues a written response.

5. The answer is distributed and implemented. The response reaches the field, the work proceeds accordingly, and the answer is filed as part of the record.

6. Any cost or schedule impact is processed. If the answer triggers a change, it flows into the change-order process; if it caused delay, that's documented.

Common RFI mistakes that cause delays

Most RFI problems trace to a handful of habits:

Vague questions. An RFI that says "please clarify" without specifics forces a back-and-forth that doubles the response time. Ask a precise, answerable question.

No due dates or tracking. RFIs without required-by dates drift, and untracked RFIs get forgotten until the work they block comes due.

No follow-up. Overdue RFIs don't chase themselves. Without someone tracking and following up, the slow ones become the delays.

Poor distribution. An answer that sits in one person's inbox never reaches the field, so the work waits anyway.

Not documenting impact. When an RFI delays work, failing to record it in the daily report loses the evidence you'd need to claim the delay.

Best practices that keep RFIs moving

Write answerable RFIs. Be specific, reference the documents, show the field condition with a photo, and propose a solution. The easier an RFI is to answer, the faster it comes back.

Log everything and set due dates. A single RFI log with required-by dates is the backbone. Review it regularly.

Follow up on overdue RFIs. Make chasing overdue responses someone's explicit job. This one habit prevents most RFI-driven delays.

Document field impact daily. When an RFI stalls work, capture it in the daily report the day it happens.

Get answers to the field fast. Make sure the resolution reaches the people building the work, not just the office.

Documenting RFI impact in the field

However you manage the RFI log itself, the field impact of RFIs belongs in your daily record — and it's the piece most often missed.

BuildLog is where that field documentation lives. When an unanswered RFI holds up work, log it in the daily report with the affected crew or activity, the date, and a photo of the condition that raised the question — building the contemporaneous, day-by-day record of what the RFI actually cost. That record is what supports a delay claim if the slow answer pushes your schedule. It works offline and exports branded PDFs, with a free tier to start.

Frequently asked questions

What is the RFI process in construction? The workflow for handling a Request for Information: a question arises, it's written and submitted, logged, reviewed and answered, the answer is distributed and implemented, and any cost or schedule impact is processed.

What slows down RFI responses? Vague questions, missing due dates, no follow-up on overdue RFIs, and poor distribution of answers. Precise, well-tracked RFIs get answered far faster.

How do you keep RFIs from delaying a project? Write answerable RFIs, set required-by dates, follow up on overdue ones, get answers to the field quickly, and document any field impact in your daily reports.


Keep the field record of every RFI impact. Try BuildLog free.

Get the BuildLog app

Write the day's report, log hours and attach photos — from the site, on your phone.

Download BuildLog on the App StoreGet BuildLog on Google Play

BuildLog is a free construction daily report app for contractors — download the app or read the guides.